Wairoa flood Mitigation Project
  • Home
  • Timeline
  • FAQ
    • Floods and Cyclone Gabrielle
    • Floodways, Spillways and Stopbanks
    • Flood Mitigation Options
    • Decision Making and Timelines
    • Potentially Impacted Home and Land Owners
    • Construction
  • Resources
    • Option 1 C+
    • Newsletters
    • Cultural Impact Assessment
    • Flood Mitigation Options - Long List
    • Flood Mitigation Options - Short List
    • Hui Presentations
    • Media Releases
    • Peer Reviews and Technical Reports
    • Videos
    • Wairoa Flood Mitigation Stakeholder Group
    • Wairoa River Bar
  • News
  • Contact
  • RIVER MOUTH GROYNE
    • What is a groyne?
    • FAQ
    • Newsletters (River Mouth Groyne)
    • Cultural Significance
    • Hui Presentations (River Mouth Groyne)
    • River Mouth Management
    • Funding
    • Have Your Say

project Timeline

Where the project started, how it has been progressing and the goals for it's completion.
Picture

SUMMER 2026/2027

Flood mitigation construction works are expected to be completed by the end of the 2026-2027 construction season. 
Picture
 SPRING 2026
​
Flood mitigation construction works expected to commence.

Picture
WINTER 2026
​Detailed design, consenting and planning work continuing.

APRIL 2026
Early enabling works, including tree clearing, completed.
Picture
FEBRUARY 2026
​
Goodman Contractors appointed as preferred contractor through an Early Contractor Involvement process.
Extensive Cultural Impact Assessment activity, including three Marae-led CIAs completed.
Resource consent has been granted and the detailed design is progressing at pace.
Picture
DECEMBER 2025
Finalising final floodway alignment and associated engineering considerations, with input from appointed contractor. Working to finalise all land access negotiations by mid-December. Early construction activity to commence before the end of the 2025/26 summer construction season.
Picture
NOVEMBER 2025
 Early contractor involvement (ECI) process completed and preferred contractor appointed. 
Picture
OCTOBER 2025​
​
Land access negotiations ongoing, project procurement strategy advancing. 
Picture
AUGUST 2025
 Cabinet approval for amended Hawke’s Bay Flood Protection Works Order 2024 received. Land access negotiations ongoing, and project procurement strategy advancing, with the Request for Proposal (RFP) for the design and construction phase released in early September. 
Picture
JUNE 2025
Land access negotiations completed for one property directly impacted by Option 1C+ with property valuations currently underway on several other properties.
Picture
MAY 2025
​
Community feedback sought on proposed legislative amendment to enable the Hawke’s Bay Flood Protection Works Order 2024 to be used for Option 1C+ 
Picture
APRIL 2025
​
The full $70 million of Crown funding ring-fenced for Wairoa is released following joint Ministerial approval of the Project Delivery Plan (PDP) based on preferred flood mitigation solution Option 1C+.
Picture
MARCH 2025
​
The Government requires a confirmed preferred flood mitigation solution, and a business case based on that preferred solution, by 31 March 2025. If this deadline is not met, the $70 million of Government funding could be withdrawn and there will be no flood mitigation for Wairoa.
Picture
FEBRUARY 2025
​
A preferred flood mitigation solution is confirmed and agreed, and publicly communicated.
Picture
NOVEMBER 2024 - FEBRUARY 2025
​
Ongoing community engagement, including with whānau and property owners potentially impacted
​ by flood mitigation solutions being considered.
Picture
NOVEMBER 2024
​
Community engagement with the broader Wairoa community commences.
Picture
OCTOBER 2024
The Tripartite partners agree to support the commencement of early engagement with mana whenua, including potentially impacted whānau and property owners.
Picture
SEPTEMBER 2024
​
Bush International Consulting’s independent rapid review of Hawke’s Bay Regional Council’s management of the Wairoa River bar is publicly released. Hawke’s Bay Regional Council also publicly releases three expert reviews to supplement the Government-commissioned review.
Picture
AUGUST 2024
​
Crown Manager, Lawrence Yule, appointed to support Hawke’s Bay Regional Council and Wairoa District Council in progressing the Wairoa flood mitigation work. Following the Crown Manager’s appointment, the scope of the programme is broadened to include both North Clyde and Kopu Road.
Picture
JULY 2024
​
Cabinet agrees to an independent rapid review of Hawke’s Bay Regional Council’s management of the Wairoa River bar following the June 2024 flooding event, to be undertaken by Mike Bush of Bush International Consulting. ​
Picture
JUNE 2024
​
Wairoa experiences a second major flooding event causing further damage to the township, with 400 flood-affected properties, a large portion of which were along Kopu Road, and 128 yellow stickered homes.
Picture
NOVEMBER 2023
​
The Wairoa Flood Mitigations Scheme Stakeholder Group meets for the first time to work through flood mitigation options. The Stakeholder Group continues to meet over an 8-month period, with input from river engineers, technical experts and mana whenua, to consider each option in more detail.
Picture
OCTOBER 2023
​
A Wairoa Flood Mitigations Scheme Stakeholder Group is established by the Tripartite partners, Wairoa District Council, Hawke’s Bay Regional Council and Tātau Tātau o Te Wairoa Trust.
Picture
AUGUST 2023
​
Hawke’s Bay’s councils finalise the terms of a cost-sharing agreement with the Government. As part of this, $70 million is specifically ring-fenced to deliver flood mitigation for Wairoa.
Picture
JUNE - AUGUST 2023
​
As a result of the Hawke’s Bay regional land categorisation process, 627 North Clyde properties were categorised as 2A with small pockets of 2P category land near Frasertown.
Picture
​FROM JUNE 2023
​
Recognising that the people of Wairoa know the whenua (land) and awa (river) best, hui were held asking local people what they knew of the river and its patterns, what they saw and experienced during Cyclone Gabrielle, and what they thought might work best for the future. From these kōrero, a list of 18 potential flood mitigation options were further developed from an engineering perspective.
Picture

february 2023

Wairoa experiences severe damage to property and infrastructure in North Clyde during Cyclone Gabrielle
Picture
Picture
If you have any questions, or if you need help or support please get in touch.
contact us
Disclaimer: The Project Team has made every effort to ensure that this information is as up-to-date and accurate as possible. We acknowledge this is a rapidly changing environment and the information provided should be used for general purposes only. We encourage people to seek additional information before making any business, legal or other decisions. If you have any queries, please don’t hesitate to contact us at [email protected]
  • Home
  • Timeline
  • FAQ
    • Floods and Cyclone Gabrielle
    • Floodways, Spillways and Stopbanks
    • Flood Mitigation Options
    • Decision Making and Timelines
    • Potentially Impacted Home and Land Owners
    • Construction
  • Resources
    • Option 1 C+
    • Newsletters
    • Cultural Impact Assessment
    • Flood Mitigation Options - Long List
    • Flood Mitigation Options - Short List
    • Hui Presentations
    • Media Releases
    • Peer Reviews and Technical Reports
    • Videos
    • Wairoa Flood Mitigation Stakeholder Group
    • Wairoa River Bar
  • News
  • Contact
  • RIVER MOUTH GROYNE
    • What is a groyne?
    • FAQ
    • Newsletters (River Mouth Groyne)
    • Cultural Significance
    • Hui Presentations (River Mouth Groyne)
    • River Mouth Management
    • Funding
    • Have Your Say